KCDC Nuraply 3PM

Kapiti Coast District Council Adminsitration Building Refurbishment

A $9.2m project over a 10-month build programme, the existing two-storey Council building was stripped back to its bare bones to enable seismic strengthening and redevelopment of the complex. A third of the original building was replaced and a new extension added with a full interior fitout. The LIG (Large Internal Gutter) shown here marks the transition between the old existing structure and the new addition. The wider overhanging roofs/ledges at the rear of the building were part of the original structure, the roof/ledge with the plinths is new.

Internal Gutter

Nuralite Nuraply 3PB/3PM torch-on double layer waterproofing membrane system to box gutter,
Fixed to 17mm H3.2 plywood
Gutter base and sides
Form upstand including timber fillet (*600mm girth)
Dress under metal roofing (*900mm girth)
Dress over lip into rainwater head
.
hover cursor over image for text, click on them for larger version
timber framing for internal gutter plywood lining for internal gutter, looking east plywood lining for internal gutter, looking west another view of plywood substrate priming the plywood, see the scale/size gutter primed with No10 adhesive ready for torchon membrane base of gutter lined with Nurabase 3mm underlay, pieces for sides ready typical side (upstand) other end marked out with the sizes of the side pieces higher side with Nurabase installed, looking east higher side with Nurabase installed, looking west part of both sides with Nurabase installed, looking east Nurabase completed base of gutter lined with Nuraply 3PM Slate finished membrane torching 3PM Slate to the base, 2.2m long pieces 3PM Slate to base and one side 3PM Slate complete at east end 3PM Slate work almost complete, looking east 3PM work complete, looking east finished, netting going on for metal roof

Front Roof

Nuralite Nuraply 3PV/3PM torch-on double layer waterproofing membrane system to overhanging roof
Form upstands to last, 250mm high
Dress under glazing
Dress through gutter including upstand
Dress into gutter
Dress to four sides of concrete plinths beneath timber fins approx 600 x 300 wide
.
hover cursor over image for text, click on them for larger version
this eyebrow roof or ledge is to have same system installed internal upstand is primed this side has to be done first so the windows can go in Nurabase underlay installed, check out the number of plinths reverse view of previous image, looking east Nuraply 3PM Slate torched to the side of the upstand reverse view from previous image, looking west and around the corner at the Rimu Rd end modified plaster screed to base of gutter to create falls, note lower 100mm is left loose Nurabase is installed in the Gutter and Nuravent base to the flat areas reverse view from previous image, looking east 3PM has been torched into the gutter and the edges scraped clean of chip for the overlaps of the sides another view of the prep work for jointing the sides east end of gutter ready for sides installing pieces under the upstand done previously inside upstand finished 3PM Slate to the flat and the sides of the plinths working on the plinths, scaffold partly down still working on those plinths nearly there, outside edge scraped ready for metal edge flashing tops of plinths done, no scaffold, rope and harness work now metal edge flashing is partly installed, lookingeast still a few bits and pieces to do membrane pieces are dressed over metal edge flashing membrane work is complete, looking east membrane work is complete, looking west membrane work is complete, Rimu Rd corner that inside corner over the building entry typical drain (no grating in) look along the outside edge reverse view from previous image view of the front of the building wooden 'vanes' installed, thats what the plinths were all about

Back Roofs

Nuralite Nuraply 3PV/3PM torch-on double layer waterproofing membrane system to overhanging roof.
Fixed to falls of concrete screed
Form upstands to last, 170mm high
Dress over H3 timber edge batten
.
hover cursor over image for text, click on them for larger version
original concrete roof left when the building was partially demolished, south side looking west original concrete roof left when the building was partially demolished, east side looking south original concrete roof left when the building was partially demolished, east side looking north original concrete roof left when the building was partially demolished, south side looking east new modified plaster screed to create slope, west side looking south new modified plaster screed to create slope, south west side looking east is it dry yet? yep its dry, good to go, primer to edge, south east side looking west east side is good for a start too east side primed south east side primed, then rained on south west ledge primed materials are loaded to the roof south east side started, Nuravent SA (self adhesive) underlay, light torching to get a good bond south east side with Nuravent SA underlay south west ledge partially done in Nuravent, Nurabase at edges and upstands east side with Nuarply 3PM Slate to flat south west ledge with Nuarply 3PM Slate to flat around corner, west ledge with Nuraply 3PM to flat upstands completed to east ledge, looking north upstands completed to south west ledge, looking north access was by scissor lift, and personal fall protection by harness and rope flat and upstands done to south east roof typical turndown edge this pipe comes down from the gutter shown earlier it has to be sealed to the lower roof membrane dressed around downpipe, and the fixing point for the hole drilling machine another downpipe penetration from above finished roof and cladding, east roof looking north finished roof and cladding, south roof looking west finished roof and cladding, south roof looking east finished roof and cladding, south west ledge, looking west