Dec-K-ing PVC to Steps and Deck

Viking Dec-K-ing PVC Membrane, Stonehenge pattern, to landing, steps, deck, ledges and posts, incl. PVC coated metal drip edge and anodised aluminium fastening bar. House renovation and extension. Oct 2014

hover cursor over image for text, click image for larger version (600×450 pixels)

main part of deck, plywood ready for laying outdoor corridor from steps to main deck area, plywood ready for laying ledge extension out from main deck area at sea side facing wall ledge extension return around other side of house, framed ready for plywood looking back at main deck area from front ledge, sea in the background front ledge and main deck area ready for Dec-K-ing membrane view from the deck coastal road to Kapiti allproof drain outlet installed very windy spot, first sheet hard to position, weights just to hold it down finally get sheet in position and glue up first half drain outlet with membrane dressed into it same outlet with grill plate more wind problems in the outdoor corridor blocked off end of corridor to reduce wind, sheet in place, glued up upstand corridor towards main deck, Kapiti Island in the background even the corflute protection sheets have to be weighted down due to the wind here front ledge with PVC coated metal drip edge installed fixing the PVC coated metal drip edge on one long sheet, upstand glued up PVC coated metal drip edge fixed to plywood on ledge extension other side of house one piece sheet half glued up Dec-K-ing finished and welded to PVC coated drip edge Dec-K-ing mitred at ledge corner completed front section ledge and main deck area completed and closed in for the night completed and closed in for the night closer view of Dec-K-ing welded to PVC coated metal drip edge first landing to steps onto deck Dec-K-ing upstand is turned into sawcut in concrete block Dec-K-ing upstand is turned into sawcut in concrete block each step and riser is a seperate piece of membrane each step and riser is a seperate piece of membrane 3 steps and risers laid and welded together wall upstand is added closer view of step wall upstand welded to step and riser lip at sides looking down on the steps and landing out side of step upstand in place and nib cap piece ready to adhere cut out detail around post reverse of post post is flashed reverse of post with flashing piece another post flashed further down the outside corridor nib capping and turndown partially in place, coastal view to Kapiti in background nib capping turndown partially in place, view towards street side of house turndown glued to fascia nib capping in place turndown hanging turndowns glued onto fascia membrane work is completed anodised aluminium fastening bar is bedded in sealant and fixed tthrough edges of PVC membrane view of fastening bar at concrete block wall fastening bar fixed to bottom edges of turndown closeup of fastening bar mitred corner closeup of fastening bar mitred corner closeup of fastening bar mitred corner view of finished landing, steps and outdoor corridor with fastening bars installed fastening bar to long length of turndown of outdoor corridor and deck reverse view of previous image fastening bar across front of deck fastening bar on north side of deck turndown job is finished, fence and railing to be installed by others

Text for images
main part of deck, plywood ready for laying
outdoor corridor from steps to main deck area, plywood ready for laying
ledge extension out from main deck area at sea side facing wall
ledge extension return around other side of house, framed ready for plywood
looking back at main deck area from front ledge, sea in the background
front ledge and main deck area ready for Dec-K-ing membrane
view from the deck coastal road to Kapiti
allproof drain outlet installed
very windy spot, first sheet hard to position, weights just to hold it down
finally get sheet in position and glue up first half
drain outlet with membrane dressed into it
same outlet with grill plate
more wind problems in the outdoor corridor
blocked off end of corridor to reduce wind, sheet in place, glued up upstand
corridor towards main deck, Kapiti Island in the background
even the corflute protection sheets have to be weighted down due to the wind here
front ledge with PVC coated metal drip edge installed
fixing the PVC coated metal drip edge on
one long sheet, upstand glued up
front ledge extension with Dec-K-ing down
PVC coated metal drip edge fixed to plywood on ledge extension other side of house
one piece sheet half glued up
Dec-K-ing finished and welded to PVC coated drip edge
Dec-K-ing mitred at ledge corner
completed front section ledge and main deck area
completed and closed in for the night
closer view of Dec-K-ing welded to PVC coated metal drip edge
first landing to steps onto deck
Dec-K-ing upstand is turned into sawcut in concrete block
each step and riser is a seperate piece of membrane
3 steps and risers laid and welded together
wall upstand is added
closer view of step wall upstand welde to step and riser lip at sides
looking down on the steps and landing
out side of step upstand in place and nib cap piece ready to adhere
cut out detail around post
reverse of post
post is flashed
reverse of post with flashing piece
another post flashed further down the outside corridor
nib capping and turndown partially in place, coastal view to Kapiti in background
nib capping turndown partially in place, view towards street side of house
turndown glued to fascia
nib capping in place turndown hanging
turndowns glued onto fascia
membrane work is completed
anodised aluminium fastening bar is bedded in sealant and fixed tthrough edges of PVC membrane
view of fastening bar at concrete block wall
fastening bar fixed to bottom edges of turndown
closeup of fastening bar mitred corner
view of finished landing, steps and outdoor corridor with fastening bars installed
fastening bar to long length of turndown of outdoor corridor and deck
reverse view of previous image
fastening bar across front of deck
fastening bar on north side of deck turndown
job is finished, fence and railing to be installed by others