Dec-K-ing to two decks

Dec-K-ing Stonehenge to two decks at Owhiro Bay. Existing house renovation.
incl 28 post boots and a deep fascia covering.
hover curser over image for text, click on image for full size (opens in new tab)

Initial Start Late June

the house, owhiro bay lower deck plywood installed some damp patches have been dried with flame torch view from other side, ready to prime plywood with adhesive view of deck from the sea side lower deck is priimed, view from deck above first sheet of Dec-K-ing membrane glued up reverse view first sheet, membrane down fascia also installed first sheet of Dec-K-ing membrane laid
Because of low temperatures, which effect the adhesive drying correctly below 10 Celcius, we stopped the installation at this point and rescheduled a restart at the end of the Winter. The builder carried on installing the fence and working on the upper deck.

Lower Deck Late October

By the end of October the temperatures had risen above 10C for extended periods of the day.
After 4 months the adhesive primer was just starting to wear off, but it had served it’s purpose over the Winter in keeping the water out of the plywood. A quick sand over and a clean and work continued on from where we left off in June.
The only issue in October is the Spring Winds, and sure enough on a couple of days work was called off due to high winds.
four months later, plywood is still sealed with primer the primer is scimmed over with a sander second sheet is ready for gluing, third sheet relaxing in the background first half of second glued sheet is laid down onto the plywood second half of secnd sheet is glued up second sheet is down, third sheet glued up same point in time, taken from deck above three sheets are laid, view across owhiro bay to cook strait and ferry crossing second and third sheets are clean, compared to 4 month old first sheet veiw of garage deck roof from below, membrane turndowns hanging loose view across the lower deck from the house, edge of sheet yet to be welded to fascia piece view across the lower deck towards the sea side of the deck view across the lower deck towards the hill side of the deck a seperate piece of membrane is installed over the small nib and welded to the feild area and the outside fascia piece the turndowns are glued and formed over a batten at the gutter edge view along the gutter edge turndown, boots to posts view along the fascia with Dec-K-ing on it reverse view along the fascia with Dec-K-ing on it view of the deck from below view out from the house from the sea side corner another view of the finished deck from the sea side detail at ground level on the sea side

Upper Deck Mid November

the upper deck on the sea side, plywood sanded ready for priming view along the upper deck back towards the hill side view along the upper deck towards the sea, fence partially installed another view at the front entrance, upper deck, owhiro bay in the background Dec-K-ing work on the upper deck starts with the installation of the membrane onto the fascia one long piece on the fascia NE corner work stopped due to high winds upper, lower decks and owhiro bay 2nd long piece being installed to the fascia 2 pieces added to the fascia on the sea side upper deck same side, top and bottom are glued and bent over onto deck and under onto soffit same side, top and bottom are glued and bent over onto deck and under onto soffit view of the turnback under onto the soffit view along the fascia upper deck front the upper deck surface needs sanding upper deck near entrance after a light sanding the outer sheet has been installed, main sheet at front entrance glued up closer view of main sheet tacking off, plank to hold edge down, quite windy planks to hold edge of main down while tacking off, quite windy front entry area is laid, one seam to weld front entrance seam is welded front porch entry, upstands front porch entry, upstand at door upstand under plaster column previously installed, now welded to main sheets back view of previous photo next part of upper deck sanded ready for installation of Dec-K-ing one sheet width will cover this area, half section folded and glued up that sheet installed additional piece required up the wall, welded to main sheet this inside side area of upper deck complete another upstand under plaster column previously installed, now welded to main sheets final area of upper deck on sea side, again one sheet coverage, a third folded back and glued up other third of single piece on sea side folded back and glued up final third of single sheet folded back and glued, plank to hold from wind lift while tacking off sea side area feild sheet installed pieces precut for fence post boots there are 23 posts, requiring 92 individual pieces to form the post boots 3 sides can be glued and installed from on the deck 8 of 10 posts have 3 of their boot sides installed and welded to feild sheet on sea side section finishing of the post boots has to be done from the outside of the fence working on the posts boots on the sea side, off scaffolding, main sheet still to be welded to fascia piece as well boots completed and main sheet welded to fascia piece reverse view of previous photo corner post completed some posts have a fat side, a packer to cover the bolts view along front of upper deck post boots completed view along front of upper deck boots and weld to fascia pieces aluminium angle bar to hold Dec-K-ing at end of deck on the sea side view along upper deck, sea side, with bottom cedar weatherboard installed boots installed, aluminium angle bar ternmination at front entrance an aluminium drip edge is fitted to the underside of the fascia to direct water away from running back under soffit view of aluminium soffit drip edge from above, front view of aluminium soffit drip edge from above, front view of aluminium soffit drip edge on sea side view of fascia and soffit angle, wooden collars fitted to fence boots, front reverse view of previous photo closer in view of previous photo raining on lower deck