Concrete Roof- Easygum

hover cursor over image for text, click image for larger version (600×450 pixels)

Fill in any deep cavities, taper off the bevel both sides from the central hump on the house roof, and rough areas around roof edge perimeter and form new covings at the base of the square concrete plinths.
Apply Easygum bitumen/rubber compound by squeege and/or broom, at the rate of 0.83m2 per litre (approx average 2mm thick) to a smooth a finish as possible and then allow to dry 48 hours.
Install Easygum lamination, Base coat at 2.5m2/litre, followed by embedding 300gram/m2 chopped strand fibreglass into base coat, followed by another coat of Easygum at 2.5m2/litre. Allow to dry 24 hours.
Apply two further coats of Easygum at increasing coverage rate.
Finish with 2 coats of Jaydex Enviroflect Aluminium for UV protective finish.
concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic concrete roof + old bitumen coating + acrylic shower of rain overnight leaving puddles on roof surface dirt trapped in rougher parts of the surface waterblasting the dirt off, SW corner waterblasting SE corner dirty east side, clean west side view over clean west side west side to east, some flaky paint removed view across roof from west to east after cleaning new bevel plastered along central hump some plaster patching, tapering on east side some plaster patching, tapering on east side some plaster patching, tapering on north west side closer view of plaster tapering and filling NW side overview od patching west side looking east to west across roof Mike grinding down patches and skimming whole surface dust from grinding dust from grinding, east side dust from grinding, west side east side dust partially swept up dust swept up east side looking north dust swept up and blown clean view over roof east to west, dust removed remaining dust blown away east side looking north west side clean and ready for coating west side and hump with first filler/primer coat of Easygum east side being first coated view across north east side, first coated view across center first coated after drying some further minor patching/filling  further minor patching/filling, white marks are for next process  further minor patching/filling, white marks are for next process  further minor patching/filling, white marks/lines are for next process Heavier second coat of Easygum is squeegeed on second coat, following white marks to ensure proper coverage rate second coat, following white marks to ensure proper coverage rate second coat, following white marks to ensure proper coverage rate last section of west side second coat second coat squeegeed on to east side second coat has J61 sand filler to add body starting on the fibreglass lamination, a plinth completed lamination on plinth, coating still wet another plinth being laminated fibreglass lamination begins on the flat roof the fibreglass is rollered into the wet Easygum fibreglass completely embedded in wet Easygum fibreglass laid out in position dry one half with fibreglass rolled into the wet Easygum same strip completed, fibreglass fully embedded next strip of fibreglass, base coat same strip, rollering fibreglass into wet Easygum base coat third strip being laid gust of wind flips dry fibreglass while setting in position same strip re set and laminated west side lamination completed another view of west side lamination completed fibreglass lamination of central hump laminating the east side fibreglass ripped to shape around plinth fibreglass being embedded in Easygum lamination complete on east side another view of east side lamination complete view over whole roof fifth coat of Easygum view over whole roof fifth coat of Easygum edges and upstands coated with Aluminium UV resistant paint edges and upstands coated with Aluminium UV resistant paint edges and upstands coated with Aluminium UV resistant paint west side being coated with Aluminium UV resistant paint east side being coated with Aluminium UV resistant paint east side being coated with Aluminium UV resistant paint east side being coated with Aluminium UV resistant paint east side coated with first coat of Aluminium UV resistant paint view of whole roof coated with first coat of Aluminium 2nd coat of Aluminium paint being applied west side 2nd coat of Aluminium paint being applied east sidefinished system view South East to North West finished system view East to West

Central Hump

Focus on various stages of system application, at central hump bevel
central hump west side before work began plastered and tapered to give even surface for fibreglass/Easygum lamination plastered bevel once dryed first coat of Easygum over hump bevel fibreglass from flat area is brought up over bevel completed second coat and fibreglass lamination over bevel first coat of Aluminium UV resistant paint completed 2nd coat of Aluminium UV resistant paint over bevel opposite side of central hump, partially dried plaster bevel opposite east side of hump plaster dried east side of hump first coat of Easygum third coat of Easygum first coat of Aluminium UV resistant paint

Close up

Focus on various stages of system application to the roof surface
close up view of surface before Easygum restoration work close up view of surface after waterblasting clean close up of surface after skim grinding to remove high points close up of surface after two filler coats of Easygum close up of surface after fibreglass/Easygum lamination close up of surface after fibreglass/Easygum lamination close up of surface first coat of Aluminium paint

Garage Roof

garage roof, bitumen coating worn away closer view of garage roof surface closer view of garage roof surface waterblasting garage roof clean some areas plastered roof dry and ready for grinding garage roof after grinding, looking south garage roof after grinding, looking north garage roof swept and blown clean rough area on middle requires extra plaster/Easygum filler coat filler coat of plaster/Easygum filler coat of plaster/Easygum second coat, Easygum filler over whole roof second coat, Easygum filler over whole roof second coat, Easygum filler over whole roof closer view of filler coat on garage roof laminating under eave of metal roof laminating main feild area of garage laminating at end of garage roof closeup of fibreglass lamination garage roof fibreglass lamination dried the next day filler coat applied the next day first coat of Aluminium UV resistant paint first coat of Aluminium UV resistant paint part way first coat of Aluminium UV resistant paint completed second coat of Aluminium UV resistant paint being applied almost there finished