TPO Dormers

This house in it’s current condition is valued at $1.45million, primarily because of it’s location in one of Wellington’s premier suburbs. The only thing between the house and the beach is a laneway and a small grassed park area.
The house is being totally renovated, inside and out, exterior work includes new cladding on one side, new metal roof, new aluminium windows, re painting and the addition of 3 new Dormers.
Enviroclad TPO (thermoplastic polyolefin) (Carlile) from Viking Roofspec was chosen as the membrane for the Dormer roofs.
When the wind is from the North it can be quite strong, so all the roofing spec’s are for the highest wind zone category. You may note in the photos where the new metal roof is shown the extra large washers under the screws.

hover cursor over image for text, click image for larger version (600×450 pixels)
the project in the initial stages dormer structure built into the existing roof screw spacing on plywood substrate the first dormer at the front of the house first sheet of TPO glued up nice location the main sheets finished another view of the first dormer a few weeks later the corrugated metal roof has been replaced, some TPO detail required TPO flange detailing on right hand side another angle of same side overview of right wing, metal roofing will overlap this detail same thing on left side note circles for extra strength in corners side view of left side second dormer, the biggest one, first sheet glued up another angle same moment first sheet is adhered tricky detail around steel beam at metal roof upstand/transition another odd angle on the right side, metal beam beneath another view of same view over the second dormer roof to Wellington Harbour, Ferry passes by second dormer done for now TPO roof vent welded to TPO roof membrane cut overflashing in position ready for welding overflashing welded to main sheet cap put on view over the second dormer roof view down on second dormer, old metal roof removed aluminium bar fitted to edge, high wind zone spec's aluminium bar fitted to edge, high wind zone spec's same detailing as dormer one at transition ends, left side completed detailing of TPO same detailing as dormer one at transition ends, right side piece of TPO drying after glue application completed detailing of TPO third roof, front door porch, before TPO TPO and vent completed view along upstand porch roof, pressure bar bedded in sealant opposite view roof vent forth dormer at front , first sheet glued up second sheet ready to go under eave completed forth dormer

text for images
the project in the initial stages
dormer structure built into the existing roof
screw spacing on plywood substrate
the first dormer at the front of the house
first sheet of TPO glued up
nice location
the main sheets finished
another view of the first dormer
a few weeks later the corrugated metal roof has been replaced, some TPO detail required
TPO flange detailing on right hand side
another angle of same side
overview of right wing, metal roofing will overlap this detail
same thing on left side
note circles for extra strength in corners
side view of left side
second dormer, the biggest one, first sheet glued up
another angle same moment
first sheet is adhered
tricky detail around steel beam at metal roof upstand/transition
another odd angle on the right side, metal beam beneath
another view of same
view over the second dormer roof to Wellington Harbour, Ferry passes by
second dormer done for now
TPO roof vent welded to TPO roof membrane
cut overflashing in position ready for welding
overflashing welded to main sheet
cap put on
view over the second dormer roof
view down on second dormer, old metal roof removed
aluminium bar fitted to edge, high wind zone spec’s
aluminium bar fitted to edge, high wind zone spec’s
same detailing as dormer one at transition ends, left side
completed detailing of TPO
same detailing as dormer one at transition ends, right side
piece of TPO drying after glue application
completed detailing of TPO
third roof, front door porch, before TPO
TPO and vent completed
view along upstand porch roof, pressure bar bedded in sealant
opposite view
roof vent
forth dormer at front , first sheet glued up
second sheet ready to go under eave
completed forth dormer