KPAC

ARDEX WPM 3000X (Shelterseal 3000X) is a self adhesive bituminous waterproofing membrane self protected by a cross-laminated HDPE film.
The high-density polyethylene film gives to the membrane characteristics of dimensional stability and ensures a uniform reaction to elongation stresses in a longitudinal and transversal direction.
This membrane has been designed and developed for the specific damp proofing of vertical walls, foundations, basements, flat and ventilated roofs.

This Project.
Ardex Shelterseal 3000X used as a waterproof membrane under the floors and foundations of a new building in Kapiti.
Single layer loose laid and lapped on the sand floor base and 2 layers self adhered to the sub walls and footing sides.
Tefond protection sheet installed before backfilling.
No ground drainage coil used on this site, based on the well graded, compact, silty sand geology.
hover curser over image for text, click on image for full size (opens in new tab)

Lift Pit

formwork/boxing for Lift Pit Floor, sand base formwork/boxing for Lift Pit Floor, sand base self-adhesive membrane is tacked face out to boxing, corner formed self-adhesive membrane is tacked face out to boxing paper backing is removed and self adhesive membrane laid face up and double lapped at internal corners the waterproofing now provides a 'tank' concrete is poured into the 'tank' concrete blockwork for lift shaft, boxing removed from floor/footing sides concrete blockwork for lift shaft, boxing removed from floor/footing sides closeup of self adhesive membrane retained on the side of the footing with a treated timber batten 300mm wide reinforcing strip is applied over the footing/wall junction, and first sheet applied up the wall one layer applied overlapping the reinforcing strip, extra excess height allowing for fold downonto future floor wired up to steel rods one layer applied overlapping the reinforcing strip, extra excess height allowing for fold downonto future floor wired up to steel rods one layer applied overlapping the reinforcing strip, extra excess height allowing for fold downonto future floor wired up to steel rods view along the base of the footing second layer of self adhesive membrane applied over first and down to bottom of footing second layer of self adhesive membrane applied over first and down to bottom of footing second layer of self adhesive membrane applied over first and down to bottom of footing double sided bitumen tape for adhering Tefond Drainge protection sheet applied partial Tefond Drainage protection sheet installed SE corner partial Tefond Drainage protection sheet installed SW corner completed wrap with Tefond Drainage protection sheet North sside completed wrap with Tefond Drainage protection sheet West side completed wrap with Tefond Drainage protection sheet SW corner Lift Pit is backfilled to floor level

Orchestra Pit

formwork/boxing for Orchestra Pit Floor, sand base formwork/boxing for Orchestra Pit Floor, sand base, footing will be 800mm high formwork/boxing for Orchestra Pit Floor, sand base, footing will be 800mm high internal lumber shuttering will be left in place, here primed ready to recieve self adhesive membrane self-adhesive membrane is tacked face out to boxing, 800mm high with a 300mm flap onto the sand sub base self-adhesive membrane is tacked face out to boxing, 800mm high with a 300mm flap onto the sand sub base double layer overlapped internal corner self-adhesive membrane is tacked face out to boxing, 800mm high with a 300mm flap onto the sand sub base laying the floor on the sand base, paper left on to provide some stablity during installation progressing with the floor membrane, the paper also removed from the vertical progressing with the floor membrane, the paper also removed from the vertical down on the floor, the 1 metre wide Shelterseal sheets are lapped to form a continious sheet half the floor is installed multiple angle changes at the east end of the pit narrow deep section of formwork, lap to loose tacked membrane on right hand side almost complete, membrane to permanent internal formwork to be done yet almost complete, end of a cold day on site almost complete east end, membrane to permanent internal formwork to be done yet almost complete west end, membrane to permanent internal formwork to be done yet rain overnight, water retained on membrane rain overnight, water retained on membrane working around the water, installing to the vertical face of the permanent internal formwork internal formwork has self adhesive stuck to it and dressed over the top and down onto the floor membrane internal formwork has self adhesive stuck to it and dressed over the top and down onto the floor membrane we are done here for now more rain over the next few days, membrane is retaining the water in the 'tank' more rain over the next few days, membrane is retaining the water in the 'tank' a day later the water is rmoved and corflute protection board laid ready for steel reinforcing cages some of the steel reinforcing has been installed the main 'beam' reinforcing being lifted into the narrow deep channel of the 'tank' Orchestra Pit floor has been poured, concrete block walls being assembled East end footing slab view along new concrete block wall on top of footing north side junction between footing and concrete block wall, some loose footing membrane the concrete block wall is primed with bitumen primer 300mm wide reinforcing strip is applied between concrete block wall and footing closer view of reinforcing strip first few sheets of membrane applied to concrete block wall, extra lap tied up to be dropped onto floor later nearing west end of north concrete block wall view along trench north wall to the west, Orchestra Pit east end footing slab and cast concrete wall, partially coated with hydroepoxy primer second primer is water based bitumen pieces relaxing after being cut from roll east cast concrete wall, first layer applied east cast concrete wall, second layer applied view along north wall to the east, second layer started view along north wall ready to install second layer view along north wall, second layer applied, release paper left behind view along north wall to the east, second layer view along north wall to the west, second layer closeup of 2nd layer, showing staggered vertical lap and reinforcing strip horizontally self adhesive squares to attach Tefond Drain to tanking view along north wall to the west Tefond Drain attached Tefond Drain protection sheet being attached to north wall, view to the east Tefond Drain protection sheet attached to north wall, view to the west Tefond Drain protection sheet attached to north wall, view to the east north side is backfilled with sand backfilled on north side east end, backfilled on north side east end footing coated with hydroepoxy primer and cast concrete wall primed with second coat bitumen primer west end footing and plinths coated with hydroepoxy primer reverse view of previous image south wall, ledge coated with hydroepoxy primer closer view of hydroepoxy primer on west slab footing top west end of footing slab partially primed with 2nd coat of bitumen primer and corner reinforcing strip applied east end footing slab coated with hydroepoxy primer south block wall and ledge coated with 2nd primer, bitumen based south block wall and east footing slab coated with 2nd primer, bitumen based south cast wall and west footing slab coated with 2nd primer, bitumen based cast wall and footing slab west end coated with 2nd primer, bitumen south wall, slabs and ledge primed with 2nd coat of primer, bitumen water has seeped behind the membrane since formwork removed membrane being repaired on the footing side membrane being repaired on the footing side membrane being repaired on the footing side membrane being repaired on the footing side membrane being repaired on the footing side 2nd layer on side of footing single layer on ledge laps over footing and up blocks reverse view of previous image 1st layer to block walls reverse view of previous image 1st layer to block walls 1st layer to block walls 1 layer to top of monolith plinth membrane turned over edge and up block walls 1st layer to block walls continues along top of monolith east end, monolith junction previously installed membrane continues from block wall above monolith to join previously installed vertical membrane view along ledge towards west monolith, 2nd layer on block wall Corflute board protection to top of monolith and ledge Tefond drainage and protection along footing below ledge Tefond drainage and protection to south facing footings and walls Tefond drainage and protection to south facing footings and walls Tefond drainage and protection to south facing footings and walls Tefond drainage and protection to south facing footings and walls Tefond drainage and protection to south facing footings and walls Tefond drainage and protection to south facing footings and walls contractor compacting sand backfill in trench south facing side of orchestra pit partly backfilled east side is fully backfilled and covered with DPC and steel mesh ready for ground floor concrete the self adhesive membrane overuns have been folded flat and the DPC taped to it

South Floor Footings

a digger scraping out the base for the south floor the south floor has been excuvated and shaped ready for tanking/damp proof course self-adhesive membrane is tacked face out to boxing, but only 300mm high on the formwork self-adhesive membrane is tacked face out to boxing, but only 300mm high on the formwork closeup of the self adhesive edge detail 300up 300 across the sand base paper is removed from the self adhesive membrane tacked to the formwork closeup of the self adhesive edge detail 300up 300 across the sand base, paper removed the self adhesive membrane edge detail is done here a few days later the damp proof course, a thick polythene sheet is laid on the floor and overlapped to the self adhesive membrane at the edges on the north side the floor will continiue through later view of the DPC overlapping the self adhesive membrane by 400mm south floor has been poured formwork removed leaving membrane on side of footing south floor has been poured formwork removed leaving membrane on side of footing some of the membrane fell off when formwork was removed bitumen primer to side of footing where membrane loose bitumen primer to side of footing where membrane loose loose membrane is restuck to footing side and freshly poured (green) concrete primed with hydroepoxy primer one layer to south floor footings overlapping underfloor membrane previously installed

Other Floor Footings

north west floor underfloor corner attached to formwork north west floor underfloor corner attached to formwork north west floor underfloor corner attached to formwork north east floor underfloor corner sections attached to formwork